Progress keeps restting

Message boards : Questions and problems : Progress keeps restting
Message board moderation

To post messages, you must log in.

AuthorMessage
Stu221

Send message
Joined: 4 Oct 20
Posts: 4
Message 100939 - Posted: 4 Oct 2020, 1:17:28 UTC

My progress keeps restting the work task was at 96% then rest back to 42% I have uninstalled Boinc and reinstlled with new task but still getting the same problem. Is this a Rositta@home, Boinc? Using Windows 10
Thanks
ID: 100939 · Report as offensive
Bryn Mawr
Help desk expert

Send message
Joined: 31 Dec 18
Posts: 284
United Kingdom
Message 100943 - Posted: 4 Oct 2020, 5:34:27 UTC - in response to Message 100939.  

My progress keeps restting the work task was at 96% then rest back to 42% I have uninstalled Boinc and reinstlled with new task but still getting the same problem. Is this a Rositta@home, Boinc? Using Windows 10
Thanks


What was happening around the time it changed? Did you sleep/turn off the machine or was it part way through an uninterrupted run?
ID: 100943 · Report as offensive
Stu221

Send message
Joined: 4 Oct 20
Posts: 4
Message 100944 - Posted: 4 Oct 2020, 6:08:46 UTC - in response to Message 100943.  

The machine had been turn off.
ID: 100944 · Report as offensive
Profile Dave
Help desk expert

Send message
Joined: 28 Jun 10
Posts: 2518
United Kingdom
Message 100945 - Posted: 4 Oct 2020, 6:33:07 UTC - in response to Message 100944.  

The machine had been turn off.
Depending on the project, different tasks will save the work to a checkpoint at various intervals. If the computer is turned off, it will go back to the last checkpoint prior to that.
ID: 100945 · Report as offensive
Profile Dave
Help desk expert

Send message
Joined: 28 Jun 10
Posts: 2518
United Kingdom
Message 100946 - Posted: 4 Oct 2020, 6:36:05 UTC - in response to Message 100944.  

The machine had been turn off.
Depending on the project, different tasks will save the work to a checkpoint at various intervals. If the computer is turned off, it will go back to the last checkpoint prior to that.

Some projects have tasks that checkpoint frequently enough that unless you are paying close attention you won't notice. Others it can be several hours work lost or over a day on slow machines for one recent batch from CPDN in testing. (The frequency of checkpoints was increased before that lot went to the main site.)
ID: 100946 · Report as offensive
Stu221

Send message
Joined: 4 Oct 20
Posts: 4
Message 100947 - Posted: 4 Oct 2020, 7:14:24 UTC - in response to Message 100946.  

I've been using rosetta@home for 10 years have never had this issue is there anyway of stopping this happening?
ID: 100947 · Report as offensive
robsmith
Volunteer tester
Help desk expert

Send message
Joined: 25 May 09
Posts: 1283
United Kingdom
Message 100948 - Posted: 4 Oct 2020, 7:34:11 UTC

One thing you could try is to see what happens if you don't shut down until the task has completed (assuming they don't stall before they get there).
Have a look at the checkpoint time on that computer - set it to 3-10 minutes, certainly not hours.
Otherwise you are in the hands of the application developers.
ID: 100948 · Report as offensive
Profile Dave
Help desk expert

Send message
Joined: 28 Jun 10
Posts: 2518
United Kingdom
Message 100949 - Posted: 4 Oct 2020, 7:41:39 UTC - in response to Message 100947.  

I've been using rosetta@home for 10 years have never had this issue is there anyway of stopping this happening?


CPDN did have one batch go out where by accident the checkpoints were a lot further apart than normal. I wonder if it is just one particular batch from Rosetta and with future batches things will go back to normal?
ID: 100949 · Report as offensive
Stu221

Send message
Joined: 4 Oct 20
Posts: 4
Message 100950 - Posted: 4 Oct 2020, 8:02:12 UTC - in response to Message 100949.  

Ok I'll see how that go's thanks for your help.
ID: 100950 · Report as offensive
Grumpy Swede
Avatar

Send message
Joined: 30 Mar 20
Posts: 372
Sweden
Message 100951 - Posted: 4 Oct 2020, 8:02:24 UTC
Last modified: 4 Oct 2020, 8:25:56 UTC

If you hibernate the computer instead of shutting down, that problem will never happen.
There are WU's on WCG for example, that has hours between checkpoints (depending on computer of course), so when running those, hibernate is the only way to stop them from jumping back hours, if you want to "pause" the computer.
ID: 100951 · Report as offensive